PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Nishimatsu Construction Co., Ltd.

西松建設株式会社

Offtaker:

Nippon Institute of Technology

学校法人日本工業大学

Industry:

Education

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

1.399MW (DC)

Inverter:

-

Generation:

2.14256GWh/year

Status and timeline

Status:

Live

Disclosed:

June 10, 2025

COD:

2025/05/01

Duration:

20

Additional details

  • Nishimatsu Construction installed a 400kW rooftop solar power plant at Nippon Institute of Technology Saitama Campus’s Main Building alongside a 999kW ground-mounted solar power plant on the campus’s premises
  • The PPA is expected to account for about 32% of the campus’s consumption

Nishimatsu Construction Co., Ltd.'s other PPAs

Nippon Institute of Technology's other PPAs

Enehub Pro - Inquiry / Quote Request

Fill out the form below to inquire about an Enehub Pro subscription. If you would like to receive a quote, please let us know your planned number of users and any add-ons you are interested in.

We typically respond within one business day.

Enter your billing information below to receive payment instructions and proceed with buying the CPPAs in 2025: Market Overview, Trends, and Opportunities report.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.