PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Ishikari Chiiki Energy LLC

石狩地域エネルギー合同会社

Offtaker:

Ishikari Saiene Data Center No. 1 LLC

合同会社石狩再エネデータセンター第1号

Industry:

-

Capacity and generation

T&D area:

Hokkaido

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

Status and timeline

Status:

Upcoming

Disclosed:

November 25, 2025

COD:

2026/04 (expected)

Duration:

Undisclosed

Additional details

  • Tokyu Land and Ishikari City’s joint venture built Hokkaido Ishikari No. 1 and No. 2 power plants on-site at Flower Communications’ Ishikari Saiene Data Center No. 1 and will supply their output to the facility’s operator

Image(s)

Ishikari Chiiki Energy LLC's other PPAs

Ishikari Saiene Data Center No. 1 LLC's other PPAs

Enehub Pro - Inquiry / Quote Request

Fill out the form below to inquire about an Enehub Pro subscription. If you would like to receive a quote, please let us know your planned number of users and any add-ons you are interested in.

We typically respond within one business day.

Enter your billing information below to receive payment instructions and proceed with buying the CPPAs in 2025: Market Overview, Trends, and Opportunities report.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.