2nd Biomass Auction (FY2019)

Status: Results announced

Overview

Subsidy scheme:

FIT

Eligible assets:

Biomass power plants using general wood with 10MW+ output and power plants using liquid biofuel

Contract period:

20 years

Price ceiling:

19.6 yen/kWh

* Price ceiling was not disclosed in advance.

Capacity sought:

120000kW

Results

Avg. awarded price:

0 yen/kWh

Succesful bids:

0

Capacity awarded:

0kW

Capacity revoked:

0kW

Net capacity awarded:

0kW

Share of capacity sought:

0%

Timeline

Business plan by:

July 12, 2019

1st deposit by:

December 5, 2019

Bid submission by:

December 6, 2019

Results announcement:

December 17, 2019

2nd deposit by:

September 17, 2019

Obtain certification by:

March 31, 2020

Remarks

  • No capacity awarded due to all bid prices (weighted average 20.55 yen/kWh) exceeding the price ceiling

Japan Energy Hub Free members can see more details about each renewable energy auction as well as parts of our other modules.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.