5th Solar Auction (FY2019 H2)

Status: Results announced

Overview

Subsidy scheme:

FIT

Eligible assets:

Solar power plants with 500kW+ output

Contract period:

20 years

Price ceiling:

13 yen/kWh

* Price ceiling was not disclosed in advance.

Capacity sought:

416191.8kW

Results

Avg. awarded price:

12.57 yen/kWh

Succesful bids:

27

Capacity awarded:

39820kW

Capacity revoked:

1940kW

Net capacity awarded:

37880kW

Share of capacity sought:

9.1%

Timeline

Business plan by:

September 9, 2019

1st deposit by:

December 5, 2019

Bid submission by:

December 6, 2019

Results announcement:

December 17, 2019

2nd deposit by:

September 17, 2019

Obtain certification by:

March 31, 2020

Japan Energy Hub Free members can see more details about each renewable energy auction as well as parts of our other modules.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.