Subsidy scheme:
FIT
Eligible assets:
Solar power plants with 250kW+ output
Contract period:
20 years
Price ceiling:
11.5 yen/kWh
* Price ceiling was not disclosed in advance.
Capacity sought:
750000kW
Avg. awarded price:
11.2 yen/kWh
Succesful bids:
83
Capacity awarded:
69400.5kW
Capacity revoked:
750kW
Net capacity awarded:
68650.5kW
Share of capacity sought:
9.2%
Business plan by:
September 3, 2020
1st deposit by:
December 17, 2020
Bid submission by:
December 18, 2020
Results announcement:
December 25, 2020
2nd deposit by:
January 15, 2021
Obtain certification by:
March 31, 2021