Subsidy scheme:
FIT
Eligible assets:
Solar power plants with 250kW+ output
Contract period:
20 years
Price ceiling:
10.75 yen/kWh
Capacity sought:
224335.7kW
Avg. awarded price:
10.61 yen/kWh
Succesful bids:
208
Capacity awarded:
233817.7kW
Capacity revoked:
45072.8kW
Net capacity awarded:
188744.9kW
Share of capacity sought:
84.1%
Business plan by:
July 16, 2021
1st deposit by:
August 19, 2021
Bid submission by:
August 20, 2021
Results announcement:
August 27, 2021
2nd deposit by:
September 10, 2021
Obtain certification by:
March 28, 2022