Subsidy scheme:
FIP
Eligible assets:
Solar power plants with 1MW+ output
Contract period:
20 years
Price ceiling:
9.63 yen/kWh
Capacity sought:
175000kW
Avg. awarded price:
9.56 yen/kWh
Succesful bids:
9
Capacity awarded:
16204.5kW
Capacity revoked:
1250kW
Net capacity awarded:
14954.5kW
Share of capacity sought:
8.5%
Business plan by:
January 27, 2023
1st deposit by:
March 2, 2023
Bid submission by:
March 3, 2023
Results announcement:
March 10, 2023
2nd deposit by:
March 24, 2023
Obtain certification by:
October 10, 2023