Subsidy scheme:
FIT
Eligible assets:
Fixed-bottom offshore wind power plants
Contract period:
20 years
Price ceiling:
34 yen/kWh
* Price ceiling was not disclosed in advance.
Capacity sought:
120000kW
Avg. awarded price:
0 yen/kWh
Succesful bids:
0
Capacity awarded:
0kW
Capacity revoked:
Net capacity awarded:
Share of capacity sought:
0%
Business plan by:
July 22, 2020
1st deposit by:
December 17, 2020
Bid submission by:
December 18, 2020
Results announcement:
December 25, 2020
2nd deposit by:
January 15, 2021
Obtain certification by:
March 31, 2021