The next issue of The Japan Power Industry Executive will be released on February 17, 2025.
Subsidy scheme:
FIT
Eligible assets:
Fixed-bottom offshore wind power plants not subject to the Sea Areas Utilization for Renewable Energy Act
Contract period:
20 years
Price ceiling:
24 yen/kWh
* Price ceiling was not disclosed in advance.
Capacity sought:
190000kW
Avg. awarded price:
0 yen/kWh
Succesful bids:
0
Capacity awarded:
0kW
Capacity revoked:
Net capacity awarded:
Share of capacity sought:
0%
Business plan by:
September 22, 2023
1st deposit by:
October 26, 2023
Bid submission by:
October 27, 2023
Results announcement:
November 2, 2023
2nd deposit by:
November 17, 2023
Obtain certification by:
June 3, 2024