Legal Matters: Navigating FEFTA notification requirements to avoid liquidity traps

Column by Keigo Kubo
·
June 5, 2026
Legal Matters

Over the past two columns, I have explored the “gap in dialect” between global sponsors and Japanese lenders regarding risk allocation and exit strategies. In this final installment, I look at a third recurring misalignment: the mismatch between regulatory timelines and project liquidity requirements.

Under Japan’s Foreign Exchange and Foreign Trade Act (FEFTA), foreign investments in designated sectors—which include power and energy storage—can trigger prior notification requirements and a statutory waiting period of 30 days. While most global sponsors anticipate this during the initial acquisition or development phase, a key point is that these requirements can also apply to subsequent emergency funding actions. This creates a potential liquidity trap.

Many standard finance documents assume that if a sponsor has liquidity, an equity cure or sponsor support action can be executed quickly, often within 10 to 20 business days. However, in a FEFTA-impacted scenario, a sponsor may have the funds and the intent to support the project yet may be legally unable to inject the capital within the required cure period due to the statutory waiting timeline. This mismatch creates a purely technical but very real risk of default, leading to avoidable waiver processes and credit committee fatigue.

Assuring lenders that “we can inject equity if needed” may not be sufficient in Japan unless you can prove the capital can be deployed within a legally available timeline, but this issue is solvable if planned for in advance.

Sponsors should negotiate cure mechanics with the statutory timeline in mind, which may include requesting longer cure periods where appropriate. It is also effective to build immediate liquidity bridges, such as prefunded reserves, or to design viable domestic funding routes that are consistent with the project’s holding structure.

Documenting a clear operational playbook—detailing who triggers the cure, which accounts are used, and what funds are immediately deployable—provides lenders with the structural clarity they require.

When misalignments over risk, exit strategies, or regulatory timelines surface only during the final documentation phase, they cost time, money, and deal momentum. The most efficient approach is to address bankability upstream at the term sheet and due diligence stages by translating global investment logic into a structure that Japanese lenders can approve with confidence.

Editor’s note: To help global sponsors and developers stress-test their structures against local expectations, TRE Legal has prepared a Bankability Briefing Note, which includes a Day-One Bankability Diagnostic Checklist. Readers interested in receiving the full PDF, please contact Keigo Kubo directly.

Disclaimer: This article is provided for general informational purposes only and does not constitute legal advice. Please seek specific advice for your particular situation.

If you found the above helpful, join our free weekly newsletter to get a summary of the latest news from the Japanese power market straight in your inbox.

…or create a FREE Japan Energy Hub account to not only receive the newsletter but also access to selected parts of our data modules.

Keigo Kubo
Attorney-at-Law
TRE Legal

Keigo Kubo is the founder of TRE Legal and a dual-qualified attorney (Japan and England & Wales). He offers a comprehensive “one-stop” service specialized in the energy sector, handling all legal aspects including development, M&A, project financing, and regulatory matters.

With over a decade of experience at Mori Hamada & Matsumoto and a secondment to Mizuho Bank’s Project Finance Department, he possesses rare versatility in bridging global investment logic with local execution. He also currently serves as Statutory Auditor for RWE Offshore Wind Japan Murakami-Tainai K.K.

Through Legal Matters, he provides practical insights on navigating Japan’s energy market.

Enehub Pro - Inquiry / Quote Request

Fill out the form below to inquire about an Enehub Pro subscription. If you would like to receive a quote, please let us know your planned number of users and any add-ons you are interested in.

We typically respond within one business day.

Enter your billing information below to receive payment instructions and proceed with buying the CPPAs in 2025: Market Overview, Trends, and Opportunities report.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.