PPA overview

Contract model and parties

Model:

Virtual

Generator:

ENEOS Renewable Energy Co., Ltd.

ENEOSリニューアブル・エナジー株式会社

Offtaker:

Amazon

Amazon

Industry:

Information Technology

Capacity and generation

T&D area:

-

Technology:

Solar

Capacity:

9.5MW (DC)

Inverter:

9.5MW (AC)

Generation:

20GWh/year

Status and timeline

Status:

Upcoming

Disclosed:

July 10, 2024

COD:

2025/11 (expected)

Duration:

20

Additional details

  • ENEOS Renewable Energy will supply power to Amazon from Kudamatsu No. 4 Solar Power Plant it is currently developing in Kudamatsu City, Yamaguchi Prefecture
  • This is Amazon’s first corporate PPA involving a utility-scale solar project in Japan

ENEOS Renewable Energy Co., Ltd.'s other PPAs

Amazon's other PPAs

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.

Enter your billing information below to receive payment instructions and proceed with buying the CPPAs in 2025: Market Overview, Trends, and Opportunities report.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.