PPA overview

Contract model and parties

Model:

Physical (off-site)

Generator:

Chugoku Electric Power Co., Inc.

中国電力株式会社

Retailer:

Chugoku Electric Power Co., Inc.

中国電力株式会社

Offtaker:

JR West

西日本旅客鉄道株式会社

Industry:

Railway

Capacity and generation

T&D area:

Chugoku

Technology:

Solar

Capacity:

90MW (DC)

Inverter:

-

Generation:

Status and timeline

Status:

Upcoming

Disclosed:

June 19, 2023

COD:

By FY2027 (expected)

Duration:

Undisclosed

Additional details

  • Chugoku EPCO plans to start power plant development for this PPA in July 2023 and build up enough capacity by the end of FY2027 to cover 10% of the power used by JR West’s shinkansen bullet trains
  • 61,000-ton annual reduction in CO2 emissions expected as a result

Chugoku Electric Power Co., Inc.'s other PPAs

JR West's other PPAs

Enehub Pro - Inquiry / Quote Request

Fill out the form below to inquire about an Enehub Pro subscription. If you would like to receive a quote, please let us know your planned number of users and any add-ons you are interested in.

We typically respond within one business day.

Enter your billing information below to receive payment instructions and proceed with buying the CPPAs in 2025: Market Overview, Trends, and Opportunities report.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.