Renova is developing 150MW and 99MW merchant grid-scale battery storage projects in undisclosed locations in addition to its previously announced pipeline, the company’s Q2 FY2026 financial results presentation released on November 12, 2026, shows.
According to the document, construction of both facilities is scheduled to begin in FY2027, with commercial operation following in FY2030. The additions bring the company’s disclosed grid-scale battery storage portfolio to 11 under-development, under-construction, and operational projects with a combined capacity of 775MW/2.3GWh.
The company expects the portfolio to generate 20-21 billion yen in revenue, 13.5-14.5 billion yen in EBITDA, and 8-9 billion yen in operating profit in FY2030. In the same period, it targets growing the pipeline to 900MW of operational and under-construction projects.
Renova commissioned its first battery storage asset, the 2MW Yasugi Power Storage Station, in April 2026. The project followed the Idemitsu Kosan-led 15MW/48MWh Himeji Power Storage Station, in which the developer holds a 22% stake.
While the developer has recently been focusing on developing merchant projects, it also has three long-term decarbonization auction-backed assets and the 30MW Ishikari Power Storage Station under a Tokyo Gas tolling deal under construction.