JR Kyushu-Sumitomo JV begins construction of 16MW/70MWh Nagasaki BESS project, targets Dec. 2028 COD

October 29, 2026
Denki no Eki Isahaya is the company’s first extra high-voltage project. (Image: JR Kyushu)

Denki no Eki, a joint venture between JR Kyushu and Sumitomo Corporation units BS Holdings and Sumitomo Corporation Kyushu, began construction of the 16MW/70MWh Denki no Eki Isahaya grid-scale battery storage facility in Isahaya City, Nagasaki Prefecture, the companies announced on October 28, 2026.

According to the statement, the facility will be built on the site of a former JR Kyushu railway substation and adjacent land, using its existing grid connection capacity. It will use 14 containerized battery systems supplied by an undisclosed manufacturer. Commercial operation is expected to begin in December 2028.

JR Kyushu and the trading company’s battery storage ownership and Kyushu units launched Denki no Eki in April 2023 to develop grid-scale battery storage on the railway operator’s unutilized land. The joint venture handles development, maintenance, and operation of the facilities.

Denki no Eki Isahaya is the company’s third and largest asset, and its first extra high-voltage facility. It follows the METI-subsidized 1.5MW/6MWh Denki no Eki Kawashiri, which was commissioned in September 2024, and the 1.5MW/6.3MWh Denki no Eki Tomiai that was brought online in March 2026. Both are located in Kumamoto Prefecture. The companies said they plan to continue developing grid-scale storage along railway lines and idle sites across Kyushu.

Sumitomo Corporation has also been developing grid-scale battery storage directly. Most recently, it secured project finance for a long-term decarbonization auction contract-backed 62MW/291MWh asset in Namie Town, Fukushima Prefecture, which is expected to be commissioned in 2029.

In other news...

Want to stay updated? Join our free weekly newsletter to get news headlines straight into your inbox.

…or create a FREE Japan Energy Hub account to not only receive the newsletter but also access to selected Enehub Indices and other data.

Enehub Pro - Inquiry / Quote Request

Fill out the form below to inquire about an Enehub Pro subscription. If you would like to receive a quote, please let us know your planned number of users and any add-ons you are interested in.

We typically respond within one business day.

Enter your billing information below to receive payment instructions and proceed with buying the CPPAs in 2025: Market Overview, Trends, and Opportunities report.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.