Eurus Energy Holdings-affiliated completed the environmental impact assessment for the up to 25.8MW Gamanosawa Omori onshore wind project in Higashidori Village, Aomori Prefecture. It submitted the final assessment on September 24 and received METI approval on October 19, 2026.
According to the document released for public viewing on November 16, 2026, the company plans to install six 4.3MW turbines across approximately 73ha. Construction is scheduled to begin around April 2027, with commercial operation expected to start in April 2030.
The holding company submitted the environmental impact assessment methodology for the project in 2009, planning a 33MW power plant at the time. It filed the draft environmental impact assessment at the same scale in August 2012, before downsizing the planned asset at the final stage.
Several other onshore wind power plants are in operation or under development in the area. Cosmo Eco Power commissioned the 27MW Shin Iwaya Wind Park in March 2025. Its up to 150MW Noushi and up to 200MW Shimokita wind farms, as well as Renova’s up to 280MW Higashidori Village project, are at the methodology stage of the environmental impact assessment process.
Eurus Energy Holdings’ portfolio includes 40 operational onshore wind power plants in Japan, according to its website. The company recently began construction of the 33.6MW Fukui Kunimi Wind Farm jointly with Tohoku Electric Power and launched the environmental impact assessment for the up to 103.2MW Itagoyayama project in Fukushima Prefecture.